The formwork from the vertical sides of beams can be removed only after?

Previouly Asked

GPSC AE CE 2021 Exam (Part B - Civil) (: 27 Nov 2021)


The formwork from the vertical sides of beams can be removed only after


  1. 1 to 2 days
  2. 3 to 4 days
  3. 5 to 7 days
  4. 7 to 14 days


Solution

Answer - 1 to 2 days

GPSC Assistant Engineer Exam Mock Test

Check the correct answer for question The formwork from the vertical sides of beams can be removed only after?. This question belongs to Reinforced Concrete Structures, Limit State Method subject. For more MCQs on these important subjects and level up exam preparation, click the topic name and start free mock test now.