The time required to complete an activity under abnormal or extremely adverse condition in which everything goes wrong, with the exception of delays due to acts which cannot be foreseen is called?

Previouly Asked

GPSC AE CE 2021 Exam (Part B - Civil) (: 27 Nov 2021)


The time required to complete an activity under abnormal or extremely adverse condition in which everything goes wrong, with the exception of delays due to acts which cannot be foreseen is called


  1. Optimistic time
  2. Most likely time
  3. Pessimistic time
  4. None of the above


Solution

Answer - Pessimistic time

GPSC Assistant Engineer Exam Mock Test

Check the correct answer for question The time required to complete an activity under abnormal or extremely adverse condition in which everything goes wrong, with the exception of delays due to acts which cannot be foreseen is called?. This question belongs to Construction Materials and Management, Project Planning, PERT subject. For more MCQs on these important subjects and level up exam preparation, click the topic name and start free mock test now.

About Us

highonstudy

Highonstudy is a rapidly growing web portal for Education News, Daily Current Affairs, Competitive Exam Preparation, Admit Card, Sarkari Results, Study Material & Free Job Alert Notification. We provide you with the latest information from the official resources.